Isle of Wight County Schools

Skip to main content
Mobile Menu
| Login
Facilities, Construction, & Maintenance » Construction of the New Hardy Elementary School

Construction of the New Hardy Elementary School

The images on this page are PRELIMINARY designs for the New Hardy Elementary School.  Images will be updated throughout the project to show the latest proposals for the facility.
Follow the progress of the new Hardy Elementary School during the pre-construction, construction, and grand opening stages. 
 
 
Timeline:
 
  • November 2020--January 2021:  Architects complete building design;  Value Engineering takes place
 
  • February 2021:  Code review for project;  Value Engineering comments addressed
 
  • March 2021:  Resubmit plan to Building Official;  CONSTRUCTION BEGINS!
 
  • Construction updates and photos will be posted monthly
 
  • December 2022:  FINAL COMPLETION!
 
 
The journey to the new Hardy Elementary School is underway, and Hardy is happening!  Click on the button above to hear Dr. Thornton discuss the current timeline for the project and explain a few of the important dates to come. Follow along with us to stay up to date on everything that is happening with this exciting project.